Free PMI Project Management Professional (PMP) Practice Question

You are managing an infrastructure development project. The project has multiple compliance requirements that span environmental, zoning, and data privacy regulations. To ensure that the project remains in full compliance, which of the following strategies would be MOST effective?

  • Organize an annual comprehensive compliance training for the project team.

  • Utilize an integrated compliance management system that is updated regularly to reflect changing regulations and requirements.

  • Conduct quarterly compliance reviews with a focus on the most recent regulatory updates.

  • Rely on external audits to address and rectify any compliance issues that arise.

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment
Your Score:

Check or uncheck an objective to set which questions you will receive.