You are the project manager for a software development project intended to automate several business processes for a client. After the initial meeting, you realized that the client has a highly complex and customized requirement including various integrations with legacy systems. What should be your next step to effectively plan the project?
Set up a series of team meetings to brainstorm potential solutions and technologies to be used.
Identify and analyze key project stakeholders to gather further detailed requirements and expectations.
Request approval from higher management to allocate additional resources to handle the complexity.
Proceed to determine the project scope directly with your core project team.