You are the project manager in an automotive manufacturing firm, and your project involves the design of a new model of car. Which of the following would be the MOST appropriate first step in developing an effective Plan Schedule Management approach?
Hold planning meetings with team members to define the scheduling methodology and the scheduling tool.
Update the project schedule model to match realistic schedule goals.
Proceed to assign staff to activities to confirm their availability and resolve any conflicts with resource calendars.
Start by defining the project milestones to determine the sequence of activities.