Your company is undergoing a major organizational change by implementing a new operational structure that influences the scope and resources of your ongoing project. What is the most appropriate first step to align the project with the new operational structure?

  • Continue with the current project plan without modifications, keeping a record of changes in case they need addressing later.

  • Inform all stakeholders about the changes but wait for further instructions before taking any action.

  • Review and update the project charter and project management plan to align with the new operational structure.

  • Initiate a new project to replace the current one, considering the extent of the organizational change is too significant.