Free PMI Project Management Professional (PMP) Practice Question

Your company is undergoing a major reorganization while you are midway through a significant project. The reorganization impacts several key project stakeholders and some are reassigned to different parts of the organization. As a project manager, what is the most appropriate immediate action to take to manage the project effectively?

  • Reevaluate the project's workflow to adjust to the reorganization.

  • Organize a meeting with the new stakeholders to establish communication and understand their expectations.

  • Ignore the organizational changes and continue with the current project plan.

  • Update your project's risk management plans without engaging with new stakeholders.

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment
Your Score:

Check or uncheck an objective to set which questions you will receive.