Free PMI Project Management Professional (PMP) Practice Question

Your project involving a specialized software deployment is nearing completion. To ensure continuity after the project closes, you plan to transfer the knowledge to the operations team that will manage the software. Which of the following would you consider the MOST effective method to confirm the knowledge transfer approach?

  • Recording a video tutorial about the software's functionality for the operations team to view.

  • Conducting interactive workshops with hands-on scenarios for the operations team.

  • Sending a detailed email to the operations team with bullet points of key processes.

  • Preparing and distributing comprehensive documentation to the operations team.