Free PMI Project Management Professional (PMP) Practice Question

Your project is halfway through its development phase when new environmental regulations are introduced, which could potentially affect multiple ongoing tasks. What should be your first step to address this situation?

  • Assess and evaluate the impact of the new regulations on the project scope and backlog.

  • Reassign affected tasks to different team members to avoid project delays.

  • Inform all stakeholders about the new regulations and their potential impact.

  • Postpone tasks that could be affected by the new regulations.

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment