Free PMI Project Management Professional (PMP) Practice Question

Your project requires adherence to strict data protection regulations. To ensure ongoing compliance, which method should you primarily implement?

  • Use standard project management methodologies.

  • Organize periodic training sessions on compliance standards.

  • Enhance system functionalities to ensure compliance.

  • Conduct regular compliance audits.

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment
Your Score:

Check or uncheck an objective to set which questions you will receive.