Your project requires adherence to strict data protection regulations. To ensure ongoing compliance, which method should you primarily implement?

  • Enhance system functionalities to ensure compliance.

  • Organize periodic training sessions on compliance standards.

  • Conduct regular compliance audits.

  • Use standard project management methodologies.