Free PMI Project Management Professional (PMP) Practice Question

Your project team has noted an increase in nonconformance issues with deliverables in the past two project reviews. What should you do next to adapt your quality management activities effectively?

  • Conduct root cause analysis to understand the cause of the quality issues and update the quality management plan to address and prevent these problems

  • Eliminate some of the quality standards to reduce the number of nonconformance issues reported

  • Continue to monitor the deliverables without making changes to see if the issues will resolve themselves over time

  • Replace the project team members responsible for the deliverable nonconformances

This question's topic:
PMI Project Management Professional (PMP) / 
Waterfall
Your Score:

Check or uncheck an objective to set which questions you will receive.