00:15:00

PMI Project Management Professional (PMP) Practice Test

Prepare for the PMI Project Management Professional (PMP) exam with this practice test. Randomly generated and customizable, this test allows you to choose the number of questions.

  • Questions: 15
  • Time: 15 minutes (60 seconds per question)
  • Included Objectives:
    • People
    • Process
    • Business Environment
    • Agile
    • Waterfall
Question 1 of 15

Your ongoing project developing software for online banking is impacted by newly implemented financial regulatory requirements. As a project manager, how should you initially evaluate the necessary actions for scope adjustment?

  • Conduct an audit on the project’s technological capabilities

  • Assess and prioritize the impact on project scope to determine necessary adjustments

  • Inform all stakeholders about the regulatory changes

  • Increase the project budget to accommodate any potential change

Question 2 of 15

The application of a hybrid methodology is recommended only for projects that have clearly defined requirements from the beginning to the end.

  • This statement is incorrect.

  • This statement is correct.

Question 3 of 15

Which of the following best describes the purpose of analyzing communication needs of project stakeholders?

  • To minimize the frequency of communication with stakeholders

  • To ensure relevant information is shared with the right stakeholders at the right time

  • To identify the most cost-effective communication channels

  • To determine the most efficient way to deliver project updates

Question 4 of 15

During a project update meeting, the project manager notices a gap in understanding between what was agreed upon for the project’s next steps and the team members' current perceptions. Which action is BEST suited to address and clarify this discrepancy?

  • Continue with the project as planned without addressing the misunderstanding.

  • Organize a dedicated meeting to specifically discuss and clarify the misunderstanding.

  • Assume that the misunderstanding will resolve itself over time.

  • Send a detailed email to all team members repeating the information.

Question 5 of 15

What factor is vital for the project manager to actively manage in the 'Control Procurements' process to maintain the integrity of contract terms and prevent unauthorized changes?

  • Prioritizing the renegotiation of contract terms to reflect the current progress of project deliverables.

  • Focusing on the resolution of claims administration outside the established contractual agreements.

  • Delegating procurement control to team members who specialize in the topic.

  • Implementing a structured change control system to manage procurement changes and contract amendments.

Question 6 of 15

If a project's Earned Value (EV) is reported as $750,000 and the Actual Cost (AC) incurred is $800,000, what is the Cost Variance (CV) for the project?

  • $750,000

  • -$50,000

  • $50,000

  • -$25,000

Question 7 of 15

Which of the following is an effective method to confirm that the performance of team members has improved after implementing new processes or training?

  • Comparing current performance data with the baseline data

  • Assessing overall team member satisfaction

  • Measuring the increase in workload managed by the team

  • Soliciting feedback from team members about their experience

Question 8 of 15

A project manager is calculating the Late Finish (LF) for an activity. The Late Start (LS) is day 15, and the activity duration is 7 days. What is the Late Finish for this activity?

  • 23 days

  • 20 days

  • 22 days

  • 21 days

Question 9 of 15

As a project manager in a software development company, you are mentoring a junior project manager who is eager but inexperienced. Considering your busy schedule, how should you approach the allocation of mentoring time to maximize its effectiveness?

  • Be available as needed, allowing the mentee to approach you anytime they need guidance.

  • Schedule regular, structured mentoring sessions based on mutual availability.

  • Organize ad hoc meetings without a regular schedule to maintain flexibility.

  • Allocate mentoring time only during specific project phases when the workload is lower.

Question 10 of 15

Your project is halfway through its development phase when new environmental regulations are introduced, which could potentially affect multiple ongoing tasks. What should be your first step to address this situation?

  • Reassign affected tasks to different team members to avoid project delays.

  • Postpone tasks that could be affected by the new regulations.

  • Inform all stakeholders about the new regulations and their potential impact.

  • Assess and evaluate the impact of the new regulations on the project scope and backlog.

Question 11 of 15

What practice is most effective for ensuring stakeholder needs and project objectives are in sync and achieving success in the project's deliverables?

  • Setting strict deadlines for stakeholder decisions

  • Establishing open communication channels

  • Frequent auditing of stakeholder activities

  • Keeping information about the project confidential from stakeholders

Question 12 of 15

As the project manager, you have identified a potential change that could significantly improve the project outcome. What should be your first step in managing this change?

  • Execute the change management process according to the project guidelines

  • Determine the strategy to handle the change, considering its impact and alignment with project goals

  • Embrace the need for change without assessing its potential impact on the project

  • Determine a change response to move the project forward and inform consulting stakeholders

Question 13 of 15

A risk with a probability of 0.3 and an impact of 0.5 has a higher risk score than a risk with a probability of 0.6 and an impact of 0.2.

  • True

  • False

Question 14 of 15

You are managing a software development project and have encountered a major issue that threatens to delay the project by several weeks. What should be your first step in resolving this issue?

  • Involve relevant stakeholders in discussing the issue and potential solutions

  • Escalate the issue to senior management before consulting stakeholders

  • Ignore the issue and hope it resolves itself to avoid difficult conversations

  • Try to solve the problem on your own before involving stakeholders

Question 15 of 15

What is the project manager's role in relation to distributing resources for team training?

  • Delegate the task of resource allocation to the human resources department

  • Develop training materials and conduct training sessions.

  • Determine training needs and budget the necessary funds, time, or materials for training programs.

  • Approve external training requests