00:15:00

PMI Project Management Professional (PMP) Practice Test

Prepare for the PMI Project Management Professional (PMP) exam with this practice test. Randomly generated and customizable, this test allows you to choose the number of questions.

  • Questions: 15
  • Time: 15 minutes (60 seconds per question)
  • Included Objectives:
    • People
    • Process
    • Business Environment
    • Agile
    • Waterfall
Question 1 of 15

What is the main purpose of conducting a Reserve Analysis in project management?

  • To assign specific risk monetary values and ensure that a fixed budget is established for each identified risk.

  • To determine the sufficiency of contingency and management reserves for handling identified and unknown project risks, respectively.

  • To complete a comprehensive financial audit of the project and submit it for stakeholder review.

  • To finalize the project budget and ensure that no further changes to financial plans are necessary.

Question 2 of 15

In a project with a Budget at Completion (BAC) of $800,000 and a current Cumulative Cost Performance Index (CPI) of 0.9, the Estimate at Completion (EAC) calculated as BAC/CPI would be less than the original budget.

  • True

  • False

Question 3 of 15

When designing a hybrid life cycle for a project, what should be the primary consideration according to the PMI's guidance?

  • Team preference for agile or predictive methods

  • Alignment with industry standards

  • Client's familiarity with PMBOK guide

  • Fit-for-purpose approach

Question 4 of 15

Servant leadership enhances team performance by ensuring that the focus of the leadership style is on the needs of team members, including the promotion of diversity and inclusion within the team.

  • False

  • True

Question 5 of 15

What compendium describes how risk management activities will be structured and performed within a project, and frequently includes elements such as risk strategy, methodology, roles and responsibilities, funding, timing, and risk categories?

  • Risk Register

  • Risk Management Plan

  • Risk Data Quality Assessment

  • Risk Report

Question 6 of 15

The best strategy to handle change in a project is to stick to the initial plan to avoid scope creep.

  • False

  • True

Question 7 of 15

What document in Project Risk Management outlines the approach, tools, and data sources that will be used to perform risk management activities, including methodologies, roles and responsibilities, funding, timing, and risk categories?

  • Risk Management Plan

  • Risk Audit Report

  • Risk Response Plan

  • Risk Register

Question 8 of 15

A project manager is facing resource constraints and needs to adjust the project schedule without changing the project duration. Which technique should they employ?

  • Resource leveling

  • Fast tracking

  • Crashing

  • Resource smoothing

Question 9 of 15

A project manager at an IT firm is nearing the completion phase of a project aimed at reducing the processing time of customer service requests. The initial project plan outlined significant benefits in the form of reduced processing times and increased customer satisfaction. Which of the following would BEST ensure that the project has a reliable system in place to track these projected benefits post-deployment?

  • Review the original project charter to assess if the stated benefits align with the project's outcomes

  • Design a user survey to gather qualitative feedback about the new system's usability

  • Conduct a series of stakeholder meetings to discuss the benefits of the project

  • Implement a set of key performance indicators (KPIs) that measure processing times and customer satisfaction rates

Question 10 of 15

You are managing a project team that's distributed across different geographical locations with varying cultures and time-zones. Which of the following actions best outlines expectations for the project’s working environment to ensure smooth collaboration and efficient communication among team members?

  • Rely on the flexibility of the team members to spontaneously communicate and collaborate as needed, without setting specific expectations.

  • Impose strict 9-to-5 working hours based on the project manager's time zone for all team members to ensure synchronicity.

  • Develop a comprehensive communication plan that includes the team's preferred communication tools, meeting schedules considering time zone differences, and expected response times for queries.

  • Schedule regular weekly meetings at a fixed time that is most convenient for the majority of the team, expecting all members to adjust accordingly.

Question 11 of 15

You are managing a project and have identified a significant technical obstacle that requires expertise outside of your team's capabilities. You have a broad network of contacts, including a former colleague who specializes in this area but left your company on unfavorable terms. Which of the following is the most appropriate approach to address this impediment?

  • Ignore the obstacle and focus on other aspects of the project

  • Attempt to solve the technical issue without seeking external expertise, even if it takes longer

  • Reach out to your former colleague immediately and request their assistance

  • Carefully consider the potential risks and benefits of involving your former colleague, and consult with your manager or legal department before making a decision

Question 12 of 15

During a project to develop a new software application, the project manager notices that the delivery of some features could be accelerated, potentially bringing forward their business benefits. Which approach should the project manager consider to deliver value incrementally?

  • Release all features at the project closure to ensure a comprehensive product launch

  • Prioritize features based on business impact and align development to release highest-impact features first

  • Focus on completing high-risk features before any other lower-risk ones, regardless of business impact

  • Extend the project schedule to accommodate more features in the initial release

Question 13 of 15

As a project manager in a manufacturing firm, you have just completed a project that automates certain production lines. After project implementation, the operational costs are reduced, but many employees are concerned about job security and overall morale is low. What is the most important next step to mitigate the negative impact on the organization?

  • Focus on communicating the financial benefits of automation to the senior management team only.

  • Organize meetings with employees to address their concerns, explaining the benefits of automation and the possibility of upskilling for newly created roles.

  • Reduce the scope of the automation project to maintain more manual processes, thus preserving more jobs.

  • Delay the further implementation of the automation processes until the organizational morale improves.

Question 14 of 15

A project manager is faced with a sudden change in project scope that requires additional resources. However, the project budget is limited, and the manager must make a decision on how to proceed. Which of the following is the BEST course of action?

  • Prioritize the project tasks and allocate resources accordingly

  • Reallocate resources from other projects to meet the new requirements

  • Overallocate existing resources to complete the additional work

  • Request additional budget to hire more resources

Question 15 of 15

The bounds of a negotiation are strictly confined to the budgetary and schedule constraints of the project.

  • This statement is incorrect.

  • This statement is correct.